How Much Concrete Does a Truck Hold in the UK?

A full ready-mix lorry holds about 7–8 m³. Type your amount, or measure your slab, to count the lorries.

By BuildersCount · Last checked 15 Oct 2026 · Our sources

How much concrete?

Which lorry?

Heidelberg Materials says a full load is 7–8 m³. We count 8 m³.

Your answer

You need
2lorries

10 m³. Lorry: Full lorry (8 m³).

  • Order10 m³
  • Last lorry2 m³

Orders under 4 m³ only: MyBuilder, a cost guide, says these often cost £30–£60 more per m³. No supplier we found publishes a fee, so we add none, as our concrete calculator does.

This answer is a guide. Ask the supplier what its lorries carry and its smallest load. For a slab or drive, check your local building rules or ask a builder or engineer.

What it costs

Ready-mix
£1,500
10 m³ × £150

Ready-mix: the middle of 7 prices from 4 UK suppliers (Oct 2026), with VAT. Delivery and any minimum charge are extra.

Quick answers

Concrete truck capacity in m³
A full load is 7–8 m³, says Heidelberg Materials. Its drum lorries come in 6 and 8 m³ sizes.
Mini-mix lorry
1–4 m³ a load, for small orders or tight access (Heidelberg).
Mix-on-site lorry
Up to 8–10 m³. Some bring as little as 0.25 m³, and one has no minimum.
Weight of a full load
About 20 tonnes of wet concrete in 8 m³. Heidelberg says its loaded 8 m³ lorry weighs about 32 tonnes.
Cost of a truck load of concrete
About £1,200 for 8 m³, at £150 per m³ with VAT. Delivery and fees are extra.

How to work it out

  1. Work out the m³ you need: length × width × thickness, in metres. Add some extra.
  2. Round up to the next 0.25 m³. Suppliers sell by the m³, so we use this step.
  3. Divide by what one lorry holds: 8 m³ for a full lorry, or 4 m³ for mini-mix.
  4. Round up. That is how many lorries come. The last one brings what is left.

10 m³ ÷ 8 m³ a lorry = 1.25
Round up: 2 lorries
Last lorry: 10 − 1 × 8 = 2 m³

Concrete lorry sizes and dimensions in the UK

Heidelberg Materials' merchant guide calls 7–8 m³ a full load. There is no one average size. Its truck page gives the measurements below. Our calculator counts 8 m³ as the volume of a full lorry.

Ready-mix lorry specifications (specs)
LorryLengthWidthHeightWeight loaded
Drum lorry, 8 m³9.15 m2.55 m3.75 mabout 32 t
Drum lorry, 6 m³8.7 m2.55 m3.75 mabout 26 t
Mini-mix, 1–4 m³7.6 m3 m3.6 mabout 18 t

Heidelberg Materials' figures. Mini-mix lorries serve Scotland, the north of England, north Wales and the West Midlands.

A drum lorry (a truckmixer, or agitator truck) transports concrete mixed at the plant. Heidelberg gives each weight loaded. We found no figure for an empty lorry.

If your supplier's lorries hold 7 m³, a big order may need one more lorry. Ask how it splits the order. In the US, trucks hold 8–12 cubic yards, says the NRMCA, a US trade group.

Lorries for common jobs

Lorry loads for common jobs
JobOrder m³8 m³ lorries4 m³ mini-mix
Shed base 3 × 2.4 m, 75 mm111
Garage floor 6 × 3 m, 100 mm211
Car drive 10 × 3 m, 100 mm3.511
Van drive 10 × 3 m, 150 mm512
House floor 10 × 8 m, 100 mm923

With 10% extra, rounded up to 0.25 m³, at least 1 m³. Our concrete calculator orders the same. Sizes are examples.

Drum lorry vs mix-on-site (volumetric) truck

A mix-on-site lorry mixes fresh concrete at your job. They are also called volumetric trucks, mobile batch plants or batching trucks. These four suppliers say what their lorries bring:

Mix-on-site lorries
SupplierMost per loadSmallest load
GPH QuickMix (Aberdeenshire)about 8 m³0.25 m³
Custom Concrete (Beds, Herts and Bucks)up to 8.5 m³no minimum
Eastern Concrete (Suffolk and Norfolk)up to 8.5 m³0.5 m³
Base Concrete (North London and Herts)up to 10 m³not stated

From each supplier's own page, checked 14 Oct 2026.

So they carry about as much as a full drum lorry. The big difference is the smallest load. Rock Solid Concrete, a drum lorry supplier, starts at 1 m³ for homes.

What a truckload of concrete costs

Ready-mix costs about £150 per m³ with VAT. That is the middle of 7 prices from 4 UK suppliers. The concrete is only part of the bill.

Cost and weight of a load
LoadConcreteWith fees, as our concrete calculatorWeight, wet
1 m³£150£9002.5 t
4 m³£600£90010 t
7 m³£1,050£1,20017.5 t
8 m³£1,200£1,35020 t

The third column adds £150 delivery, the middle of Checkatrade's £100–£200. It also adds Mister Concrete's minimum charge, £750 with VAT.

  • Small loads, under 4 m³: MyBuilder, a cost guide, says these often cost £30–£60 more per m³. No supplier we found publishes a fee, so we add none, as our concrete calculator does.
  • Minimum orders: Checkatrade says most suppliers' minimum order is around £500.

For prices by mix, see our concrete cost calculator.

Will the lorry reach? Access, chute and waiting time

Makers ask for a clear gap about 3.5 m wide and 4 m high, on firm ground. Heidelberg's chute reaches about 2.75 m past the back of the lorry.

If it can't get that close, you can barrow the concrete or hire a pump. About 35 barrow loads make 1 m³, says Heidelberg. So an 8 m³ lorry is about 280 barrow trips.

Heidelberg gives 30 minutes to unload for free. MyBuilder says waiting then costs £2–£3 a minute. Have barrows and helpers ready.

Before the lorry comes

  1. Work out the m³ with our concrete calculator. Add 10% extra.
  2. Ask what the lorries hold, the smallest load and any small-load fee.
  3. Check the gate and drive: about 3.5 m wide and 4 m high.
  4. Ask how far the chute reaches, and if it has extensions. Plan where it or a pump will reach.
  5. Have tools, barrows and helpers ready before pouring starts.
  6. For a slab or drive, check your local building rules or ask a builder or engineer.

Questions people ask

How much concrete is in a mixer truck?

A full load is 7–8 m³, says Heidelberg Materials. A mini-mix lorry brings 1–4 m³.

How does a cement mixer truck work?

A ready-mix (drum) lorry brings concrete mixed at the plant. A mix-on-site lorry mixes fresh concrete at your job instead.

How much does a full concrete lorry weigh?

Heidelberg says its 8 m³ lorry weighs about 32 tonnes (32,000 kg) loaded. The wet concrete alone is about 20 tonnes.

What is the smallest load of ready-mix?

Rock Solid Concrete takes home orders from 1 m³. Mix-on-site firms bring less: from 0.25 m³, or with no minimum.

How wide is a concrete lorry?

About 2.55 m across the body, says Heidelberg. Makers ask for a gap about 3.5 m wide and 4 m high.

How long can a concrete lorry wait?

Heidelberg gives 30 minutes to unload for free. MyBuilder, a cost guide, says waiting then costs £2–£3 a minute.

Where our numbers come from

Made by BuildersCount. Last checked 15 Oct 2026.