Tarmac Calculator
Find how many tonnes of tarmac (asphalt) you need for a drive, path or patch.
Measure your project
Your answer
That is 2.55 m³.
If you buy bags
A drive needs a firm base under the tarmac. The MPA gives 150 mm of hardcore, such as Type 1. Check your local building rules or ask a builder or engineer.
What it costs
Cold-lay: £13.80 a bag with VAT, from only 2 stores, so a rough guide. Laid by a pro: about £90 per m², the middle of 7 cost-guide and contractor figures (VAT not stated). Get local quotes.
Quick answers
- A 10 × 3 m drive, 85 mm thick
- About 5.99 tonnes of tarmac.
- Tonnes of tarmac in a m³
- About 2.35 tonnes, once rolled. Cemex gives 2.26 to 2.56 by mix, but its top figure may be high (see below).
- Tarmac depth or thickness for a driveway
- 25 mm on top and 60 mm below, over 150 mm of base, says the Mineral Products Association.
- What one tonne covers
- About 17 m² at 25 mm thick. Heidelberg gives 14–18 m².
How to work it out
- Work out the area of the drive or path in m²: length × width. Know it? Tap “m²” and type it in.
- Choose the rolled thickness: one layer or both. Change mm to metres by dividing by 1,000.
- Area × thickness gives the m³ of finished tarmac.
- Rolled tarmac is about 2.35 tonnes per m³. So m³ × 2.35 gives the tonnes to order.
10 × 3 × 0.085 = 2.55 m³
2.55 × 2.35 = 5.99 tonnes
Tonnes of tarmac by drive size
Each row is one drive. The first two columns are single layers; the last adds both together. For other sizes, use the calculator above.
| Drive | Top, 25 mm | Lower, 60 mm | Both, 85 mm |
|---|---|---|---|
| 5 × 3 m | 0.88 | 2.11 | 3.00 |
| 6 × 3 m | 1.06 | 2.54 | 3.60 |
| 8 × 3 m | 1.41 | 3.38 | 4.79 |
| 10 × 3 m | 1.76 | 4.23 | 5.99 |
| 10 × 5 m | 2.94 | 7.05 | 9.99 |
| 12 × 6 m | 4.23 | 10.15 | 14.38 |
Rolled thickness, with nothing extra for edges.
How thick a tarmac drive should be, layer by layer
The Mineral Products Association (MPA) gives this build for a private drive:
- Top layer: 25 mm. This is the surface you see.
- Lower layer: 60 mm of a mix called AC 20.
- Base: 150 mm of hardcore, such as Type 1.
The top layer depends on the stone size in the mix. Heidelberg's Tuffdrive sheet gives 20–30 mm for a 6 mm mix. It gives 30–40 mm for a 10 mm mix.
A UK government guide to front gardens gives 200–250 mm for a whole drive. It was written for drives that let rain soak through (permeable).
For a 10 × 3 m drive, the 150 mm base is about 9.4 tonnes of Type 1. Our Type 1 calculator works out yours.
How thick should tarmac be laid?
Hot tarmac goes down loose and thick. The roller then presses it to its final depth. For dense mixes, the Asphalt Institute says to lay it about 1.25 times as deep as the finished layer. Open mixes sink less, about 1.15 times.
The weight you order does not change.
| Finished | Dense mix | Open mix |
|---|---|---|
| 25 mm | 31 mm | 29 mm |
| 60 mm | 75 mm | 69 mm |
| 85 mm | 106 mm | 98 mm |
How many wheelbarrows in a tonne of tarmac?
No supplier gives a figure, so we worked it out. A tonne of rolled tarmac is about 426 litres. Loose, it takes about 1.25 times the room: 532 litres.
A builder's barrow holds 85–90 litres. So a tonne is about 6 barrows, full to the brim. Each load would weigh about 160–170 kg. Smaller loads mean more trips.
Your drive will hold the weight of cars. Check your local building rules or ask a builder or engineer.
Tarmac per square metre
Supplier calculators, like Heidelberg's and Cemex's, work in tonnes. This table turns a thickness into kg per m², and m² per tonne.
| Thickness | Per m² | One tonne covers |
|---|---|---|
| 20 mm | 47 kg | 21.3 m² |
| 25 mm | 59 kg | 17 m² |
| 30 mm | 71 kg | 14.2 m² |
| 40 mm | 94 kg | 10.6 m² |
| 60 mm | 141 kg | 7.1 m² |
| 85 mm | 200 kg | 5 m² |
Heidelberg says a tonne covers 14–18 m² at 25 mm. Our figure sits inside that.
Why tonnes differ between mixes
Some mixes are heavier than others. Cemex gives a weight for each mix. Here is a 10 × 3 m drive at 85 mm with each one.
| Mix | Per m³ | Tonnes |
|---|---|---|
| AC open or medium (Cemex) | 2.26 t | 5.76 |
| Our figure | 2.35 t | 5.99 |
| HRA (Cemex) | 2.45 t | 6.25 |
| AC dense (Heidelberg) | 2.5 t | 6.38 |
| AC dense (Cemex) | 2.56 t | 6.53 |
Cemex's AC dense figure looks high next to its HRA figure. Heidelberg's calculator works out at about 2.5 for AC dense.
Ask your supplier which mix they will lay.
Cold-lay tarmac bags
Cold-lay tarmac comes in 25 kg bags. Wickes says one bag covers about 0.4 m² at 30 mm thick. Our middle price is £13.80 a bag with VAT. That is from only 2 stores, so treat it as a rough guide.
Bags add up fast on a whole drive. Here is a 10 × 3 m drive:
| Thickness | Bags | Weight | Cost |
|---|---|---|---|
| 30 mm (Wickes figure) | 75 | 1.9 t | £1,035 |
| 85 mm (scaled up) | 213 | 5.3 t | £2,939 |
Wickes gives cover at 30 mm only. The 85 mm row is our sum from that figure. Cost with VAT.
Buying hot tarmac by the tonne, or paying a firm to lay a drive? Our tarmac driveway cost calculator gives those prices. It adds digging out and a new base too.
Questions people ask
How much tarmac do I need?
Take the drive's area in m² and its rolled thickness in metres. Multiply them, then multiply by 2.35 for tonnes. Or type your sizes into the calculator above.
How do you calculate tarmac tonnage?
Find the volume: m² × thickness in metres. Then multiply by 2.35. A 10 × 3 m drive at 85 mm needs about 6.0 tonnes.
How much tarmac per square metre?
About 59 kg per m² for a 25 mm top layer. Both drive layers, 85 mm, take about 200 kg per m².
How many m² does a tonne of tarmac cover?
About 14–18 m² at 25 mm thick, says Heidelberg Materials. Our sums give about 17 m².
What base do you need for tarmac?
The Mineral Products Association puts 150 mm of hardcore base under a tarmac drive. Marshalls uses MOT Type 1 for drive sub-bases.
How thick should tarmac be on a driveway?
About 85 mm in two layers, says the Mineral Products Association. That is a 60 mm binder course below and a 25 mm surface course on top.
How much does a bag of cold-lay tarmac cover?
About 0.4 m² at 30 mm thick, says Wickes, for a 25 kg bag.
Do you need planning permission to tarmac a front garden?
Not in England if it lets rain soak through, like porous asphalt, or drains to a lawn or border. Over 5 m² of ordinary tarmac that drains to the road needs permission, says a UK government guide. Wales and Scotland have their own rules.
Where our numbers come from
- Asphalt weight: Asphalt Institute (110 lb per square yard per inch)
- Top layer by mix: Heidelberg Materials Tuffdrive data sheet
- Tarmac coverage: Heidelberg Materials asphalt calculator (14–18 m² per tonne at 25 mm)
- Tarmac weight by mix: Cemex asphalt calculator
- Tarmac drive layers: Mineral Products Association, Asphalt Applications 1
- Marshalls: sub-base depths; MOT Type 1 for driveways
- UK government guide to paving front gardens
- Type 1 weight and price: Wickes 800 kg bag (checked Oct 2026)
- Cold-lay bag: Wickes Tarmac Cold Lay Macadam (25 kg covers about 0.4 m² at 30 mm)
- Cold-lay price: 2 UK stores (25 kg, Oct 2026)
- Laid tarmac price: the middle of 7 cost-guide and contractor figures (6 checked again; VAT not stated)
- JT Atkinson, Walsall Contractor builders wheelbarrow: 85 L; £53.99 inc VAT
- Travis Perkins, Haemmerlin pre-assembled steel wheelbarrow: maximum load 90 L; £61.74 inc VAT
Made by BuildersCount. Last checked 16 Oct 2026.