Sand and Cement Calculator

Find how much sand and cement you need for brick or block mortar, or a floor screed.

Made by BuildersCount · Last checked 14 Oct 2026 · Our sources

Measure your job

What are you making?
What kind of wall?
Which mix? (cement : sand)
Extra for spills

No UK source gives a waste figure, so we start at 0%. Pick 5% or 10% if you want some spare.

Your answer

You need about
3bags of cement

For about 450 bricks (single brick wall), mixed 1 : 5.

3
bags of cement (25 kg)
68 kg
1
bulk bag of building sand
0.45 tonnes
24
or bagged mortar mix (20 kg bags)
19 bricks a bag

Bulk bags are 800 kg. Bags are rounded up.

This answer is a guide. For footings, walls or anything that holds weight, check your local building rules or ask a builder or engineer.

What it costs

Mix your own
£93
Cement £25 + Building sand £67

UK middle prices from October 2026, with VAT. Cement: £8.39 a 25 kg bag (7 prices from 3 sellers). Bulk bags: £75, building sand £67.35 (3 sellers each). Few prices, so treat them as a rough guide.

Quick answers

1,000 bricks at 1 : 5
About 1.0 tonne of building sand and 6 bags of cement.
Bricks and blocks per m²
About 60 bricks in a single brick wall, and 120 in a double wall. About 9.88 blocks.
Screed mix (BS 8204)
1 : 4 cement to sharp sand by weight, says the MPA. It can go from 1 : 3 to 1 : 4.5.
Screed, 10 m² at 50 mm (1 : 4)
About 8 bags of cement and 800 kg of sharp sand.

How to work it out

  1. Measure the wall or floor in metres. Multiply length × height (or width) for m².
  2. For a single brick wall, multiply by 60 to get bricks.
  3. Allow about 1 kg of building sand for each brick.
  4. For a 1 : 5 mix, add 150 kg of cement for each tonne of sand.
  5. Divide the cement by 25 for bags. Round up.

1,000 bricks × 1 kg = 1,000 kg of sand
1.0 tonne × 150 kg = 150 kg of cement
150 ÷ 25 → 6 bags

Sand and cement for bricks

The Brick Development Association and the Mineral Products Association (MPA) are trade bodies. Both say a tonne of mortar lays about 1,000 bricks. So we allow about 1 kg of building sand per brick.

The MPA gives kg of cement for each tonne of lime and sand, by mix group. We match those groups to plain sand mixes and work out the bags. Where it gives two figures, we use the higher one.

Cement for each tonne of building sand
MixCement25 kg bags (our sum)Class
1 : 3250 kg10M12
1 : 4190 kg7.6M6
1 : 5150 kg6M4
1 : 6150 kg6M4

Classes are from Heidelberg's cement data sheet.

Which mix?

Gilmore Building Supplies says 1 : 5 is a common mix for bricks. Screwfix says 1 : 4 suits standard walls. For a wall that holds weight, check your local building rules or ask a builder or engineer.

Litres of mortar per brick? See our brick mortar calculator.

Sand and cement per m² of brickwork or blockwork

Per m² of wall, at 1 : 5
WallBuilding sandCementBricks or blocks
Single brick wall60 kg9 kg60 bricks
Double brick wall131 kg19.6 kg120 bricks
100 mm blocks15 kg2.3 kg9.88 blocks

Bricks per m² from Travis Perkins, blocks from Kilsaran. No extra added.

We worked out the double wall and block figures. Blue Circle and Cemex give the mortar. For the sand in it, we use the MPA's lime and sand figure. The MPA has none for plain sand and cement.

Makers disagree on blocks. Per m³ of mortar, Blue Circle says about 1,500 blocks and Kilsaran, an Irish maker, about 800. We use Cemex's 1 litre a block. That is near the middle of the UK and Irish range, 0.67 to 1.25 litres. See our block mortar calculator.

Sand and cement for a patio (laying slabs)

Marshalls lays patio slabs on a full bed of wet mortar, 30–40 mm thick. Tamped down, it ends up about 25 mm. Under it goes a 100 mm packed sub-base.

How to mix mortar for a patio

Marshalls mixes 1 part cement to 3 or 4 parts sharp sand. The Concrete Society also uses 1 : 4, by volume (buckets, not kg).

Patio mortar for paving slabs: how much per m²?

Order for the bed before tamping: at 40 mm, each m² takes 40 litres of mortar. We have no reliable weight for this mix, so no kg yet.

Sand and cement render

The MPA's render data sheet uses two coats on a wall. The first coat is 10–12 mm, scratched and left to dry. The top coat is about 8–10 mm.

On ordinary brickwork, mix the first coat at 1 part cement to 5 or 6 parts sand, by volume. The top coat is weaker: 1 : 6 or 1 : 7. Both use a plasticiser or lime.

One m³ of render covers about 100 m² at 10 mm thick.

Sand and cement for a floor screed

The table shows the British Standard (BS 8204) screed mix and both limits, by weight, as the MPA gives them.

Our estimate: cement + sharp sand per m², in kg
Thickness1 : 41 : 31 : 4.5
40 mm16 + 6420 + 6014.5 + 65
50 mm20 + 8025 + 7518.2 + 82
65 mm26 + 10432.5 + 9823.6 + 106
75 mm30 + 12037.5 + 11327.3 + 123

By weight, with no extra. 40 mm · bonded, 50 mm · unbonded (minimum), 65 mm · floating, 75 mm · over underfloor heating.

How we got these figures

No UK source we found gives this for screed you mix yourself. Bagged mixes from Kilsaran and Heidelberg use about 1.82 to 1.96 kg per m² for each mm. Mapei's goes up to 2 kg. We use 2 kg, that top figure, and split it by your mix.

Before you buy

  1. Extra: we found no UK figure for extra mortar or screed, so the calculator starts at 0%.
  2. Prices, with VAT: cement about £8.39 a bag, building sand £67.35 and sharp sand £75 a bulk bag. Each comes from only 3 sellers, so treat them as a rough guide.

Questions people ask

How much sand and cement do I need for 1,000 bricks?

For a single brick wall at 1 : 5, allow 1.0 tonne of building sand. Add 150 kg of cement, which is 6 bags of 25 kg.

How many bags of cement to a tonne of sand?

For a tonne (1,000 kg) of sand, MPA figures give 10 bags of 25 kg for 1 : 3. At 1 : 5, it is 6 bags.

How many bulk bags of sand for 1,000 bricks?

About 1.25 bulk bags of 800 kg, which means buying 2. Heidelberg's building sand sheet puts one bulk bag at about 900 bricks.

How much sand and cement per m² of brickwork?

For a single brick wall at 1 : 5, about 60 kg of sand and 9 kg of cement. A double wall needs about 2.2 times as much.

How much sand and cement for 100 blocks?

About 154 kg of building sand and 23 kg of cement, at 1 : 5. That is 1 bag of 25 kg. It uses Cemex's 1 litre of mortar per block and the MPA's sand figure.

How much sand and cement do I need for render?

On brickwork, the MPA's first coat is 1 cement to 5 or 6 sand, by volume. Add plasticiser or lime. 1 m³ covers about 100 m² at 10 mm.

How much sand and cement do I need for a floor screed?

Each m² at 50 mm and 1 : 4 takes about 20 kg of cement. Add about 80 kg of sharp sand.

How much sand and cement do I need for a patio?

Marshalls lays slabs on a 30–40 mm bed of mortar. It mixes 1 part cement to 3 or 4 parts sharp sand. At 40 mm, that is 40 litres of mortar per m².

Where our numbers come from

Made by BuildersCount. Last checked 14 Oct 2026.