Crusher Run Calculator
Find how many tons of crusher run you need. Crusher run is crushed stone mixed with stone dust. We allow for packing it down.
Measure your project
Your answer
That is 13.55 cubic yards before packing. We added 10% extra.
Could be 16.39–23.71 tons.
About 28 trips in a half-ton pickup, about ½ cubic yard (0.7 tons) each. Or 3 small dump trucks (5 cubic yards each). Check your pickup's payload first.
Wet ground, laid on fabric, may need 8 in. A shed builder's guide says to pack it in layers of 4 in or less. Under a house slab, the IRC asks for clean graded stone. One shed maker we checked asks for clean stone too.
What it costs
Price is the middle of 5 US suppliers' prices (Oct 2026), per ton, before delivery. Ask your supplier for their price.
Quick answers
- How many tons in a yard?
- About 1.4 tons of loose stone. Packed down, a yard weighs about 1.86 tons.
- How much does a ton cover?
- About 44 sq ft at 4 in deep, packed. About 29 sq ft at 6 in.
- How deep?
- Driveway: 6 in, packed. Patio or path base: 4 in.
- Other names
- Crush and run, or crush n run. 21A, CR-6, DGA, QP, ABC and road bond are local names for similar stone.
How to work it out
- Measure the length and width in feet. If you know the square feet, tap “Sq ft” instead.
- Pick the depth after packing, in inches. Divide by 12.
- Multiply length × width × depth, then divide by 27. This gives packed cubic yards.
- Crusher run packs down, so multiply by 1.33. This gives loose cubic yards to order.
- Multiply loose cubic yards by 1.4 to get tons.
50 × 10 × 0.5 = 250 cubic feet
250 ÷ 27 = 9.26 cubic yards packed
250 ÷ 27 × 1.33 = 12.31 loose
250 ÷ 27 × 1.33 × 1.4 = 17.24 tons, before extra
Add 10%: 18.96 tons
Crusher run for common driveway sizes
Find your driveway size, then read across to your depth. Each depth is measured after packing.
The tons already include the extra loose stone that packs down.
| Driveway | 4 in deep | 6 in deep | 8 in deep |
|---|---|---|---|
| 10 × 20 ft | 4.6 | 6.9 | 9.2 |
| 10 × 40 ft | 9.2 | 13.8 | 18.4 |
| 10 × 50 ft | 11.5 | 17.2 | 23.0 |
| 12 × 50 ft | 13.8 | 20.7 | 27.6 |
| 12 × 100 ft | 27.6 | 41.4 | 55.2 |
| 20 × 20 ft | 9.2 | 13.8 | 18.4 |
| 20 × 40 ft | 18.4 | 27.6 | 36.8 |
No extra is added here. The calculator adds 10% to start, as one supplier advises.
What one ton covers
The deeper you go, the less ground a ton covers. These numbers are for stone that has been packed down.
| Depth after packing | One ton covers |
|---|---|
| 2 in | 87 sq ft |
| 3 in | 58 sq ft |
| 4 in | 44 sq ft |
| 6 in | 29 sq ft |
Why some yards say a ton covers more
Some yards print bigger numbers. One yard in South Carolina says a ton covers 70 sq ft at 4 in. A yard in Georgia says 80 sq ft.
The South Carolina yard calls its figure packed, but works it out from a loose weight. The Georgia yard does not say. Packed stone is heavier for its size, so a ton covers less.
At 4 in packed, plan on about 44 sq ft per ton. Ordering by a bigger number can leave you short.
How deep for each job
All depths below are after packing.
- Driveway for cars: 4–6 in. Our calculator starts at 6 in.
- Delivery trucks and RVs: 8–10 in.
- Farm machines: 12 in or more.
- Wet ground, on fabric: 8 in, says a US farm road standard. Dry, firm ground can take 4 in.
- Base under asphalt: 6–8 in.
- Base under pavers: 4 in for a patio, and 6 in for a driveway.
Under a slab or a shed
The IRC, the model code for US homes, covers a house floor below ground level. It asks for a base of 4 in of clean graded sand, gravel or crushed stone. Ground that drains well may not need it. The code does not name crusher run.
One shed maker we checked, White Pine Structures, asks for a pad 4–6 in deep. It wants 3/4 in clean crushed stone, not pea gravel or river stone. Clean stone lets water drain away. Crusher run has stone dust in it, so it drains less well.
These are general guides. For a driveway or anything that holds weight, check your local building rules or ask a builder or engineer.
Crusher run names by state
The pieces in crusher run go from about 3/4–2 in down to fine dust. That mix is what lets it pack so hard.
Crusher run is a road base. Kentucky's road specs call this kind of stone dense graded aggregate base (DGA).
Yards in different states call it different names. Use your local name when you phone a yard.
| Name | Where you may hear it |
|---|---|
| 21A, 21B | Virginia |
| CR-6 | Maryland |
| 2A | Pennsylvania |
| Item 4 | New York |
| 304 | Ohio |
| DGA | Kentucky |
| QP | Maryland, New York, New Jersey |
| Road stone | Maryland |
| ABC, road bond | South and North Carolina |
| 21AA | Michigan |
| Class 5 | Minnesota |
| #53 | Indiana |
| Class 6 | Colorado |
Each state's mix of stone sizes is a little different. So these are alike, but not the same.
Ordering and spreading
Our middle price is $54.95 a ton, from 5 sellers in MD, GA, SC and NC. Our crusher run cost guide covers small loads and delivery.
Spreading it
- Spread no more than 4 in of stone at a time, as one shed builder's guide says.
- Pack each layer with a plate compactor before you add the next.
- Keep the stone damp. A US farm road standard says a squeezed handful should hold together as a ball.
- Check the depth after packing, and top up low spots.
Questions people ask
How much crusher run do I need for my driveway?
A driveway for cars needs about 6 in, packed. At that depth, a 10 × 50 ft driveway takes about 17.2 tons, before extra. With the calculator's 10% extra, order 19.0 tons.
How many tons of crusher run are in a cubic yard?
About 1.4 tons, loose off the truck. Packed down, a cubic yard holds about 1.86 tons. Suppliers and road agencies give 1.21–1.75 tons a cubic yard for loose stone or for ordering.
How many cubic feet are in a ton of crusher run?
About 19.3 cubic feet of loose stone. Once packed, a ton fills about 14.5 cubic feet.
How much does 1 ton of crusher run cover?
About 44 sq ft at 4 in deep, packed. At 2 in, about 87 sq ft. Some yards quote more, because they skip the packing.
How much does crusher run compact?
It packs down by about a quarter. Penn State spreads 8 in of loose stone to get 6 in packed. So order about a third more than the packed amount.
How thick should crusher run be?
About 6 in, packed, for a car driveway. Use 8–10 in for trucks and RVs. A patio or path base needs 4 in.
How many tons of crush and run do I need for a patio?
A paver patio needs a base at least 4 in deep, packed. A 12 × 12 ft patio at that depth takes about 3.3 tons, before extra.
Where our numbers come from
- Crusher run weight: the middle of 9 suppliers and road agencies
- Packing down: Penn State road-stone guide (8 in loose packs to 6 in)
- Driveway depth: Gravelshop driveway layers guide
- Wet ground needs more stone: USDA NRCS access road standard (Ohio)
- Thin layers: a shed builder's guide (4 in; archived page) and NRCS New York (9 in)
- Driveway thickness and care: Colorado Asphalt Pavement Association
- Paver base and bedding sand: CMHA paving guide (4 in patio base, 6 in driveway)
- Base under a slab: US home building code (IRC R506.2.2)
- Shed pad depth: a shed maker's site guide (White Pine Structures)
- Other names for crusher run: state and supplier names (research)
- Crusher run price: the middle price of 5 suppliers in MD, GA, SC and NC (Oct 2026)
- Crush & run, #57 stone and mulch bags: Mulch Pros (Cumming, GA)
- Product price feed: Piedmont Landscape Materials (Concord, NC)
- Crusher run: Palmetto Sand & Gravel (what a ton covers; free delivery from 15 tons; add 10%)
- What a yard says a ton covers: Golden Landscaping Supply, GA
- Smallest delivery, 5 tons: Champion Builder Supply, MD
- Price for one ton at a time: Bert & Mary Supply, MD
- Pickup truck loads: Texas Soil and Stone
- Dump truck loads: McCarty Mulch & Stone, Indiana
Made by BuildersCount. Last checked 9 Oct 2026.
How we work out our numbers About us Found a mistake? Tell us
Cite this page
BuildersCount. (2026, October 9). Crusher Run Calculator. https://builderscount.com/crusher-run-calculator/