Concrete Footing Calculator

Find the concrete for footings, column pads and piers. Measure in feet or metres, and see the sizes the building code (Part 9) asks for.

Made by BuildersCount · Last checked 4 Oct 2026 · Our sources

Measure your project

I measure in
Footing
Depth here means how thick the footing is, not how deep you dig
Extra for spills

We add 10% to start, as Sakrete's US slab calculator does.

Your answer

You need about
0.45cubic yards

That is 12.2 cubic feet, or 0.35 m³. We added 10% extra.

If you buy bags

25
bags of 30 kg
750 kg in total

Each 30 kg bag makes 0.014 m³, or 0.5 cubic foot.

If you order a truck (ready-mix)

Ask for 1.00 m³ (about 1.31 cubic yards). Ontario plant lists start at 1 m³, so we price at least that.

Footings hold up the building. Check your local building rules or ask a builder or engineer.

Which costs less?

Bags
$175
25 × 30 kg
Truck
$667
1.00 m³ + small-load fee + fees
Bags cost $492 less

But you must mix 25 bags by hand. That is 750 kg to lift.

Pouring from 1 Nov to 30 Apr?

Ready-mix (25 MPa): the middle of 4 lists from 3 companies in Ontario and Calgary. Footings need at least 15 MPa. Bags: the middle of 8 prices at 5 Ontario stores. October 2026, before GST/HST.

Quick answers

Footing width, outside walls
250, 350 or 450 mm for 1, 2 or 3 storeys, says the building code (Part 9).
How deep under a house
In clay or unknown soil, at least 1.2 m (4 ft), says the building code (Part 9). With no heated space, also go below the frost line.
40 ft of footing, 10 × 4 in
0.45 cubic yards (0.35 m³) with 10% extra. Or 25 bags of 30 kg.

How to work it out

  1. Measure the footing length in feet. Measure the width and thickness in inches.
  2. Change the inches to feet: divide each by 12.
  3. Multiply length × width × thickness for the volume in cubic feet. Divide by 27 for cubic yards.
  4. Add 10% extra. Add any column pads and piers the same way.

250 mm → 10 in wide. 100 mm → 4 in thick
40 × 0.833 × 0.333 = 11.1 cubic feet
11.1 + 10% = 12.2 cubic feet
12.2 ÷ 27 = 0.45 cubic yards

Concrete footing sizes in the code (Part 9)

Column pads assume columns 3 m apart.

Smallest footing sizes, Table 9.15.3.4
StoreysOutside wallsInside wallsColumn pad
1250 mm (9.8 in)200 mm (7.9 in)0.4 m² (4.3 sq ft)
2350 mm (13.8 in)350 mm (13.8 in)0.75 m² (8.1 sq ft)
3450 mm (17.7 in)500 mm (19.7 in)1 m² (10.8 sq ft)

From Part 9 (BC Building Code 2018 and Ontario Building Code 2024 text).

  • Brick on the outside: add 65 mm for each storey of brick facing. Add 130 mm for each storey of solid masonry walls.
  • Wet ground: where the water table is high in gravel, sand or silt, make the footing 2 times as wide.
  • Who it is for: the table is for houses on soil that holds at least 75 kPa. Joists must be up to 4.9 m long, and floor loads up to 2.4 kPa. Longer joists need a wider footing, worked out by a code formula. On weaker soil, an engineer must design the footing instead.

How thick: the sticking-out rule

A footing must be at least 100 mm thick, and as thick as it sticks out.

Example: 2 storeys with brick

Start at 350 mm. Add 65 mm for each of the 2 brick storeys: 480 mm wide.

Say it sits under a 150 mm concrete wall, the least in BC's 2024 code, in the middle. It sticks out 165 mm each side, so it must be at least 165 mm (6.5 in) thick. Your drawings set the real wall size.

How deep: frost and the 1.2 m rule

The code gives no frost depth for any city. It sets 1.2 m as the least depth in clay or unknown soil.

Least depth of foundations, Table 9.12.2.2
SoilHeated basementNo heated space
RockNo limitNo limit
Coarse grained soilsNo limitNo limit if it drains well; below frost depth if not
SiltNo limitBelow frost depth
Clay or soils not clearly defined1.2 m1.2 m, and below frost depth

'No heated space' covers decks, unheated garages, piers and footings with insulation. Same Part 9 text as above.

Cities can ask for more

Winnipeg asks for 1.8 m (6 ft) under decks with joists more than 1,300 mm up. The rest of Manitoba asks 1.8 m (6 ft) once joists are more than 600 mm up.

For deck and pier depths in other cities, see the sonotube calculator. Check with your own city.

Low "floating" decks, up to 55 m² (about 592 sq ft), can skip frost footings. The questions below list every limit.

Concrete and steel for footings

Footings need at least 15 MPa concrete. Dufferin's 15 MPa footing mix is $254, on one Ontario list.

If you add bars, keep 75 mm of concrete between them and the soil, says Nanaimo's city spec. See the rebar calculator.

Dig down to soil nobody has moved, and pour on that. Footings hold up the house, so check your local building rules or ask a builder or engineer.

Questions people ask

How big should a concrete footing be?

Under an outside wall, 250 mm wide for 1 storey, 350 mm for 2 and 450 mm for 3. That is Canada's Part 9 table for houses on firm soil.

How thick should a concrete footing be?

At least 100 mm. It must also be at least as thick as it sticks out past the wall or column.

How deep does a concrete footer or footing need to be?

In Canada, it depends on the soil and on heat. In clay or unknown soil, the building code (Part 9) asks for at least 1.2 m. With no heated space, go below the frost line too. Winnipeg and Manitoba ask 1.8 m for decks.

What strength of concrete do footings need?

At least 15 MPa, says the building code (Part 9).

Do footings need rebar in Canada?

Part 9 has no rebar rule for house footings. It covers plain or lightly reinforced concrete. Footings designed as reinforced concrete need an engineer (Part 4).

Does a deck need footings below the frost line?

Not a low "floating" deck. That means 1 storey, up to 55 m², with joists no more than 600 mm up. It must have no roof and not be attached. Other decks follow the depth rules and your city.

How big should a column pad be?

The building code (Part 9) asks for 0.4 m² for 1 storey, with columns 3 m apart. That is about 632 mm square.