BuildersCount

Concrete Slab Calculator

Find how much concrete a slab or pad needs, in cubic metres or bags, and what goes under it.

Made by BuildersCount · Last checked 4 Oct 2026 · Our sources

Measure your project

Slab or pad
House slab, shed pad, path, patio or drive
How thick is the slab or pad?
Extra for spills

We add 5%, as Allied Concrete suggests.

Your answer

You need about
0.76m³

We added 5% extra.

If you buy bags

95
High Strength RapidSet, 20 kg
1,900 kg in total
76
HandiCrete, 25 kg
1,900 kg in total
48
HandiCrete, 40 kg
1,920 kg in total

Dricon says each 25 kg bag of HandiCrete makes about 0.01 m³.

If you order a truck (ready-mix)

Ask for 0.80 m³. We round up to the next 0.2 m³.

This is a guide. For a house slab, drive or anything that holds weight, check your local building rules. Or ask a builder or engineer.

Which costs less?

Bags
$1,403
76 × 25 kg
Truck
$353
0.80 m³ + small-load fee
A truck costs $1,050 less

You also skip mixing 76 bags by hand. Have the edges ready before it comes.

NZ prices from October 2026, with 15% GST. 25 kg bag: middle of 6 sellers. Ready-mix: one merchant's 20 MPa price. We add Allied's $115 small-load fee to every truck. One merchant lists it, and the load size it applies to isn't stated. Set it to $0 if your order is big enough.

Quick answers

A 3 × 2.4 m shed pad, 100 mm thick
0.72 m³. With 5% extra, 0.76 m³. That is 76 bags of 25 kg, or 0.8 m³ of ready-mix.
Garden shed pad
At least 80 mm in the middle and 100 mm at the edges, says Duratuf, a NZ shed maker.
Vibrate it?
Yes for house slabs and drives, say CCANZ and the placers' code. A small pad can be tamped by hand, says Golden Bay.

How to work it out

  1. Find the area: length times width, in metres. The answer is in m².
  2. Choose how thick the slab will be. In metres, 100 mm is 0.1 m.
  3. Multiply the area by the thickness. Now you have m³.
  4. Allow 5% more for spills and low spots.
  5. Order that m³ as ready-mix, or divide it by 0.01 for 25 kg bags.

3 × 2.4 = 7.2 m²
7.2 × 0.1 = 0.72 m³
0.72 + 5% = 0.756 m³
0.756 ÷ 0.01 = 75.6 → 76 bags

How to calculate concrete volume for a slab or pad

Area × thickness gives the volume. Here are some common jobs.

Concrete for common slabs and pads
Jobm³ (+5%)Ready-mix to orderTruck cost25 kg bags
Shed pad 2.4 × 1.8 m, 100 mm0.450.6 m³$29346
Path 10 × 0.9 m, 75 mm0.710.8 m³$35371
Pad 3 × 3 m, 100 mm0.951 m³$41295
Driveway 15 × 3 m, 100 mm4.734.8 m³$1,542473

Truck cost at one merchant's 20 MPa price of $297.28 per m³ with GST, plus Allied's $115 small-load fee. We add that fee to every load.

Garden shed pads: thickness and consent

The Building Act does not say a shed needs a concrete base. Duratuf, a NZ shed maker, says a timber floor kit or a concrete pad both work, on level ground.

  • Garden shed: Duratuf says at least 80 mm thick in the middle, and 100 mm at the edges. Make it 15 mm narrower and 15 mm shorter than the shed, so the cladding runs past the floor.
  • Bigger shed: for one bigger Lifestyle shed, Duratuf asks for a 100 mm slab with 200 mm thick edges. It sits on at least 75 mm of fill, with 20 MPa concrete and 665 or SE62 mesh.

Building consent (Schedule 1)

  • Up to 10 m²: no consent for a detached, single-storey shed. Its floor can be up to 1 m off the ground, and it can be up to 3.5 m tall. It can't have a toilet, stored water or a bed.
  • 10–30 m²: no consent if it is lightweight and built to B1/AS1, a set of approved building methods. Or if a licensed building practitioner (LBP) builds it. Either way, it must be at least 1 m from any boundary or house.

Our 3 × 2.4 m example is 7.2 m², under the 10 m² line. Check with your council too.

House slab rules (NZS 3604)

BRANZ and CCANZ explain NZS 3604 in two guides from Dec 2011. They are summaries of the standard. We could not check the government's site for later changes.

A house slab, from the ground up
LayerWhat the guides say
Hardfill (gravel fill)75–600 mm, packed down in layers of up to 150 mm
Sand blinding25 mm, so the DPM does not tear
DPM (damp-proof sheet)Usually 0.25 mm polythene, joins taped
MeshGrade 500E, at least 2.27 kg/m² (e.g. SE62), 30 mm below the top
Concrete100 mm. 17.5 MPa, or 20 MPa if exposed to the weather in zone C, 25 MPa in zone D
Under inside load-bearing wallsThicken to 200 mm, unless the wall carries only the roof of a one-storey house

From BRANZ Bulletin 541 and the CCANZ slab guide. MPa is the strength. Zones B, C and D are NZS 3604 exposure zones, set by where you build.

500E mesh is ductile: it bends a long way before it snaps. Grade 500N 665 and 668 mesh do not meet the rule for house slabs. CCANZ keeps slab bays to 6 m or less, and 5 m is better.

For a house slab, check your local building rules or ask a builder or engineer.

Mesh in a slab, drive or path

Mesh by job
JobConcreteMeshJoints
House slab100 mm500E, 2.27 kg/m² or moreBays up to 6 m
Driveway100 mm or more665 or 668Saw cuts every 3 m
Path75 mmnone or 668Every 3 m or less
Thicker paving150 mm663–

Sources: BRANZ and CCANZ, and the placers' driveway code (NZMCPA).

Mesh holds cracks closed. CCANZ says it does not add load capacity or let you pour thinner. CCANZ does not advise a driveway with no mesh.

How many sheets of SE62 mesh?

United Steel's SE62 sheet is 4.45 × 2.02 m. With 200 mm laps, each sheet covers 7.56 m². So a 10 × 12 m slab takes 16 sheets. Ask your merchant to check.

Concrete driveway: base, slope and joints

The NZ concrete placers' driveway code says:

  • At least 100 mm thick. Trucks or heavy vehicles need a designed slab.
  • 20 MPa concrete or stronger.
  • A base of 100 mm of GAP 20, a quarry gravel, packed down.
  • A slope (fall) of at least 1:100. That is 10 mm per metre, so 150 mm along a 15 m drive.
  • Saw-cut joints every 3 m, 1/4 of the slab deep, 24–48 hours after the pour.
  • Keep it wet for at least 4 days.

For a drive, check your local building rules or ask a builder or engineer.

Vibrating the concrete

The placers' code says all driveway concrete must be vibrated. CCANZ says house-slab concrete must be too. Allied Concrete says to vibrate or rod it.

For a small DIY pad, Golden Bay says hand tamping works, though vibration is best. Tamp with a thick timber on edge, or use a vibrating beam.

No vibrator? CCANZ's path guide says to order a wetter mix: a 120–130 mm slump. Ask the plant for it, rather than adding water.

Questions people ask

Does a garden shed need a concrete base?

The Building Act does not ask for one. A 10–30 m² lightweight shed must be built to B1/AS1, which covers foundations too. Duratuf, a shed maker, says a timber floor or a concrete pad both work.

Do I need mesh in my concrete slab?

Yes for a house slab: Grade 500E mesh of at least 2.27 kg/m² (NZS 3604, as summed up in 2011). Yes for a drive: 665 or 668 mesh. A 75 mm path can have none or 668 mesh if joints are 3 m apart or less.

Do you need to vibrate a concrete slab?

Yes for a house slab, says CCANZ. The placers' code says all driveway concrete must be vibrated. For a small DIY pad, Golden Bay says hand tamping works, but vibrating is best.

Do I need building consent for a shed?

Not for a detached, single-storey shed up to 10 m² that meets set rules. From 10 to 30 m², none if it meets set rules. One rule: at least 1 m from boundaries and houses.

How much hardfill goes under a concrete slab?

For a house slab, 75–600 mm, packed down in layers of up to 150 mm. The driveway code asks for 100 mm of GAP 20.

How many sheets of mesh do I need?

Divide the slab area by 7.56 m² for United Steel's 4.45 × 2.02 m SE62 sheet, then round up. A 6 × 4 m slab takes 4 sheets.

Where our numbers come from

Made by BuildersCount. Last checked 4 Oct 2026.